Line Charges for Commercial & Industrial sites with half-hour metering on the Northpower network (excluding GST)
Effective 1st April 2012

Price Plan Applicable charges excluding metering Tariff Code Availability per day Total line charge from 1/04/11 Total line charge from 1/04/12   Transmission portion of total line charge from 1/04/2012
ND9 (Code 9) Monthly Customer charge D 24 hours $113.00 $120.00 $/month 0%
Demand-based Anytime Demand Charge 09AD   $5.40 $5.55 $/kVA/month 41%
(68 ICP's) Shoulder Demand Charge 09SD   $7.05 $8.00 $/kVA/month 59%
  Reactive Power charge 09RP   $2.41 $2.41 $/excess kVAr/month 100%
               
ND10 (Code 10) Daily Customer charge J 24 hours 244.00 260.00 cents/day 0%
Consumption HH commercial 31   9.45 10.30 cents/kWh 28%
   (71 ICP's) Reactive Power charge 31RP   3.00 3.00 cents/excess kVArh 100%

Methodology for ND9 “Code 9” charges

  • The Anytime Demand is the highest half-hour demand at any time between 1 April and 31 March, with a minimum chargeable demand of 150kVA.
  • The Shoulder Demand is the average of the six highest daily half-hour demands from 0700-1000 and 1700-2130 from 1 May to 30 September, with a minimum chargeable demand of 150kVA.
  • Both the Anytime and Shoulder Demand Charges are charged in every month of the year.
  • The Reactive Power Charge is currently assessed on the basis of a 0.95 lagging power factor coincident with the highest half-hour demand each month.

Methodology for ND10 “Code 10” charges

  • The ND10 Price Plan is an alternative for ICP’s with half-hour metering where the ND9 Price Plan is unsuitable.
  • The Reactive Power Charge is assessed on the basis of an average 0.95 power factor over an entire month.

Note:  ND 9 and ND10 are only available at ICP’s with half-hour metering.  Switches to or from ND9 and ND10 can only be made on the first day of a month.